<p> <strong>SCEGC Equipment Installation Group New Energy Co., Ltd</strong> </p> <p> <img src="http://es.sxnec.com/upload/image/20181018/20181018142542_65332.png" alt="" width="30" height="30" title="" align="" />&nbsp;029-83663581&nbsp; </p> <p> <img src="http://es.sxnec.com/upload/image/20181018/20181018142011_12337.png" alt="" width="30" height="30" title="" align="" />&nbsp; sjxny@sxnec.com&nbsp; </p> <p> <img src="http://es.sxnec.com/upload/image/20181018/20181018142527_75385.png" alt="" width="30" height="30" title="" align="" />&nbsp;17F, Building 17, Fengcheng 9th road, Weiyang Dist., Xi 'an City, 710018 China </p> <p> <br /> </p> <p> <span></span> </p>

Key Project Current Position:HOME > Key Project

  •      Luneng·Yijun 49.5MWp PV Power Generation Project was invested by Shaanxi Luneng Yijun New Energy Co.,Ltd and contracted to build by SCEGC Group New Energy Co.,Ltd.

         This project is located in Bazhangyuan Village, Yaosheng Town, Yijun County, Tongchuan City, Shaanxi Province. 

         The total installed capacity of the project is 49.5MW. As of November 30, 2018, the project has basically completed construction and grid-connected work, and is currently undergoing final commissioning. The detailed completion progress is as follows:


    • 1. The shortage of civil power in the booster station is being eliminated;
    • 2. The pouring construction of the roof of the booster warehouse is completed, and the appearance of the flag platform has been completed (not constructed this year due to weather);
    • 3. The disputed work tool problem is completed;
    • 4. The station of the booster station is processed and the station is intuitively completed;
    • 5. The test of the Institute of Electric Power is completed;
    • 6. Handling individual faulty inverters;
    • 9. The photovoltaic area has been completed by weeding and turning over, waiting for acceptance;
    • 10. The photovoltaic zone fence installation is completed;
    • 11. The 16 areas of the rod rust removal have been completed;
    • 12. The standardization construction of the national network in the booster station is completed.



  • Since June 30, 2018, the project began to check for gaps and eliminate gaps on the second day after it was fully connected. The main tasks are as follows:
    First, light volley area
    1, PV field road construction
    2, stent foundation pile head corrosion protection construction
    3, the installation of support slant rod
    4, ground flat iron welding and paint
    Installation of masonry, plaster and fencing for changing the base of the box
    6, back filling of box change foundation, field level
    7, connecting between components
    8, the connection between the groups of flat iron
    9, confluence box, inverter, communication box shell grounding
    10, flow box, inverter, communication box fire closure
    11, Box change steel ladder installation
    Switching station area
    1, switching station site hardening construction
    2, switch station lighting, video monitoring construction
    3, switching station gate construction
    4, switch station equipment basic dust
    5, switch station equipment basic railing installation
    6, switch station equipment basic steps masonry




    Welding and painting of grounded flat iron

       

    Construction of gate of switch station

     

    Installation of basic railings for switching station equipment

  • Luneng Yijun 49.5 MW photovolt power station project construction progress Luneng Yijun 49.5 MW photovolt power station project was invested by Shaanxi Luneng Yijun New Energy Co., Ltd., Shaanxi Jiangong Installation Group New Energy Co., Ltd. total package construction.
    This project is located in Baizhang Village, Yusheng Town, Yijun County, Tongchuan City, Shaanxi Province, with a total installed capacity of 49.5 MW. As of July 18, 2018, the number of personnel on the scene: Shaanxi Jiangong 15, supervision 6, upward pressure station 14, outside line 106 people. Construction progress in the light voltage-area: a total of 44.43 megawatts were completed for the brackets, and 88.86 % were completed. A total of 40.93 MW was completed for the component and a total of 81.86 % was completed; 4 collection lines completed 3 lines and a total of 85 % was completed. The pressure station accumulates 97 % of the progress achieved. Line completion: 1, 66 foundation front group tower accumulated 65 bases(a total of 1 base without group tower). The 2, 66 base rear group tower accumulates 48 bases(completed by the group tower). 3, the group tower completed a total of 113 4, the line to complete 67 # -77 #(4044 meters): 1 ground line, 3 wires. 1 cable; 77 # -89 #(4373 M): 1 ground line, 3 wires, 1 cable; 89 # -103 #(4736 meters): 1 ground line, 3 wires, 1 cable; 110 # -114 #: 1 ground line, 1 wire; 1 # -2 #: 1 ground line, 3 wires. 1 cable; 6 # -13 #: 1 ground line, 3 wires